AMERICAN ENERGY ATLAS
Industrial + power·New Jersey

Montclair State University

Montclair, Essex County, New Jersey · PJM · operated by Cartier Energy, LLC · owned by Montclair State University

2023 · headline year
Fuel spend$6.22M2023 · estimate
Capacity in service11.8MW3 units · gas
Net generation47GWh2023 · reported
CO₂ emitted36,784t2023 · reported to EPA · 4,320th highest of 6,030 in the US
Rank in New Jersey#54of 407 · by capacity · #5,195 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor46%2023

Location

Essex County · PJM · RFC

What it burns

2023 · reported

Share of reported fuel consumption

99% Natural gas · 581,899 MMBtu · reported · $6.04M est.1% Oil & petroleum · 7,700 MMBtu · reported · $181,104 est.

Natural gas supplies 99% of the fuel energy it burned in 2023.

CO₂ emitted, t · 2011–2023

020,00040,00060,000201120172023
Reported (through 2023)

Generating units

3 of 3 shown · 11.8 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit CTG-16.4Natural GasNatural Gas Fired Combustion Turbine2013Operating
Unit ENG-12.7Natural GasNatural Gas Internal Combustion Engine2018Operating
Unit ENG-22.7Natural GasNatural Gas Internal Combustion Engine2018Operating

All 3 units shown. Behind each one, AEA holds the full engineering record: co-firing fuels and fuel-switching times.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Parent company
Montclair State University · 100%
Operating utility
Cartier Energy, LLC
Entity type
Commercial
Regulatory status
Not Regulated
Industry sector
Other
EPA facility ID
1002987
Balancing authority
PJM
NERC region
ReliabilityFirst (RFC)
EIA plant ID
63501

Common questions

How big is Montclair State University?
11.8 MW across 3 generating units in service.
Who owns and operates it?
Owned by Montclair State University (100%) and operated by Cartier Energy, LLC, filed as commercial.
Which grid does it sell into?
PJM (PJM Interconnection, LLC) is its balancing authority, inside NERC's ReliabilityFirst region.
How old is it?
The capacity-weighted average megawatt here came online in 2015. The oldest operating unit is Unit CTG-1 (2013); the newest are Unit ENG-1 and Unit ENG-2 (2018).
When is it due to retire?
No retirement date has been filed for any operating unit at Montclair State University. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas and oil & petroleum.
How much does it spend on fuel?
An estimated $6.22M in 2023 — natural gas $6.04M and oil & petroleum $181,104. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.
How much CO₂ does it emit?
36,784 t in 2023, reported to the EPA — the 4,320th highest of 6,030 US facilities that reported. Up from 34,102 t in 2011.

Also at this site

Montclair Cogen FacilitySame site · retired→

Related pages

New Jersey energyAll facilities in the state→McGraw Hill Solar12.0 MW operating capacity→ Pennsauken Brownfield Solar12.0 MW operating capacity→ JMB Mcguire-Dix-Lakehurst Solar Project11.4 MW operating capacity→ Phillips 66 BAYWAY REFINERY11.2 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming