Meadow Springs Renewable Energy (Hybrid)
White County, Illinois · MISO · operated by Vesper Energy Development LLC
Capacity shown is planned or not in service
Proposed
A planned 300 MW batteries project, filed to come online in 2026.
Planned capacity300MW2 units · not yet in service
Location
Generating units
2 of 2 shown · none in service
All 2 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.
See the engineering record →
Ownership & operations
- Operating utility
- Vesper Energy Development LLC
- Entity type
- Independent Power Producer
- Regulatory status
- Not Regulated
- Balancing authority
- MISO
- NERC region
- SERC
- EIA plant ID
- 67986
Common questions
How big is Meadow Springs Renewable Energy (Hybrid)?
300 MW across 2 units, none of which is in service — all planned.
Who owns and operates it?
Operated by Vesper Energy Development LLC, filed as independent power producer.
Which grid does it sell into?
MISO (Midcontinent Independent Transmission System Operator, Inc.) is its balancing authority, inside NERC's SERC region.
What does it run on?
Batteries (150 MW) and Solar Photovoltaic (150 MW).