Camden, Ouachita County, Arkansas · MISO · operated by Arkansas Electric Coop Corp · owned by Arkansas Electric Cooperative Corp

2023 · headline year
Fuel spend$1.37M2023 · estimate
Capacity in service136MW1 unit · gas
Net generation41.1GWh2023 · reported
CO₂ emitted27,347t2023 · reported to EPA · 4,952nd highest of 6,030 in the US
Rank in Arkansas#25of 108 · by capacity · #1,982 (tied) of 13,147 US
Reported suppliersNot reported2023 · last deliveries 2012
Capacity factor3%2023

Location

Ouachita County · MISO · SERC

What it burns

2023 · reported

Share of reported fuel consumption

100% Natural gas · 509,249 MMBtu · reported · $1.37M est.

CO₂ emitted, t · 2011–2023

050,000100,000150,000201120172023
Reported (through 2023)

Generating units

1 of 1 shown · 136 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 1136.0Natural GasNatural Gas Steam Turbine1972Operating

1 unit shown. Behind it, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; co-firing fuels and fuel-switching times; NOₓ, particulate and mercury controls with compliance years; cooling system and water source with withdrawal rate; stack height.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023. 21 deliveries are on record for 2011–2012.

Delivery history. Subscribe to see every recorded delivery, supplier, mine of origin and transport mode.

See the delivery history →

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Arkansas Electric Coop Corp
Entity type
Cooperative
Regulatory status
Regulated
Industry sector
Power Plants
EPA facility ID
1006593
Balancing authority
MISO
NERC region
SERC
Gas pipeline
Enable Gas Transmission LLC
EIA plant ID
203

Common questions

How big is McClellan?
136 MW across 1 generating unit in service.
Who owns and operates it?
Owned by Arkansas Electric Cooperative Corp (100%) and operated by Arkansas Electric Coop Corp, filed as cooperative.
Which grid does it sell into?
MISO (Midcontinent Independent Transmission System Operator, Inc.) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 1972.
When is it due to retire?
No retirement date has been filed for any operating unit at McClellan. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas.
How much does it spend on fuel?
An estimated $1.37M in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.
How much CO₂ does it emit?
27,347 t in 2023, reported to the EPA — the 4,952nd highest of 6,030 US facilities that reported. Down from 148,586 t in 2011.

Related pages

Arkansas energyAll facilities in the state→Fulton155 MW operating capacity→ Driver Solar150 MW operating capacity→ Woodruff County Solar122 MW operating capacity→ Searcy Solar Hybrid110 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming