AMERICAN ENERGY ATLAS
Power·Arkansas

Lee Creek Water Treatment Facility

Crawford County, Arkansas · MISO · operated by City of Fort Smith

Capacity shown is planned or not in service

Out of service
Out-of-service capacity1.3MW1 unit · none in service

Location

Crawford County · MISO · MRO

Generating units

1 of 1 shown · none in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 02091.3WaterConventional Hydroelectric1992Out of service

1 unit shown. Behind it, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Ownership & operations

Operating utility
City of Fort Smith
Entity type
Municipally Owned Utility
Regulatory status
Not Regulated
Balancing authority
MISO
NERC region
MRO
EIA plant ID
54283

Common questions

How big is Lee Creek Water Treatment Facility?
1.3 MW across 1 unit, none of which is in service — all on standby or out of service.
Who owns and operates it?
Operated by City of Fort Smith, filed as municipally owned utility.
Which grid does it sell into?
MISO (Midcontinent Independent Transmission System Operator, Inc.) is its balancing authority, inside NERC's MRO region.
What does it run on?
Conventional Hydroelectric (1.3 MW).

Related pages

Arkansas energyAll facilities in the state→Jefferson Power StationPower facility→ Judsonia Compressor StationIndustrial facility→ Lion SolarPower facility→ Little Red River Compressor StationIndustrial facility→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming