AMERICAN ENERGY ATLAS
Industrial + power·Florida

Lee County Solid Waste Resource Recovery Facility

Fort Myers, Lee County, Florida · FPL · operated by Lee County Board-Commissioners · owned by State of Florida

2023 · headline year
Fuel spend$7,4022023 · estimate
Capacity in service59.0MW2 units · waste
Net generation274GWh2023 · reported
CO₂ emitted241,749t2023 · reported to EPA · 1,396th highest of 6,030 in the US
Rank in Florida#210of 310 · by capacity · #3,281 (tied) of 13,147 US
Reported suppliersNot reported2023 · last deliveries 2011
Capacity factor53%2023

Location

Lee County · FPL · SERC

What it burns

2023 · reported

Share of reported fuel consumption

99% Other fuels · 5.2 TBtu · reported1% Oil & petroleum · 0.0335 TBtu · reported · $7,402 est.

Other fuels supplies 99% of the fuel energy it burned in 2023.

CO₂ emitted, t · 2011–2023

0100,000200,000300,000201120172023
Reported (through 2023)

Generating units

2 of 2 shown · 59.0 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit GEN139.0Municipal solid wasteMunicipal Solid Waste1994Operating
Unit GEN220.0Municipal solid wasteMunicipal Solid Waste2007Operating

All 2 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; SO₂ scrubber type, sorbent and removal efficiency; NOₓ, particulate and mercury controls with compliance years.

See the engineering record →
UnitEventWhenMW
Unit GEN1retirement2029-0939.0 MW
Unit GEN2retirement2072-0820.0 MW

Who supplies the fuel

2023
No fuel deliveries are reported for 2023. 12 deliveries are on record for 2011.

Delivery history. Subscribe to see every recorded delivery, supplier, mine of origin and transport mode.

See the delivery history →

In the Atlas

Open in the Atlas →

Ownership & operations

Parent company
State of Florida · 100%
Operating utility
Lee County Board-Commissioners
Entity type
Municipally Owned Utility
Regulatory status
Not Regulated
Industry sector
Waste
EPA facility ID
1002268
Balancing authority
FPL
NERC region
SERC
EIA plant ID
52010

Common questions

How big is Lee County Solid Waste Resource Recovery Facility?
59.0 MW across 2 generating units in service.
Who owns and operates it?
Owned by State of Florida (100%) and operated by Lee County Board-Commissioners, filed as municipally owned utility.
Which grid does it sell into?
FPL (Florida Power & Light Company) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 1998. The oldest operating unit is Unit GEN1 (1994); the newest is Unit GEN2 (2007).
When is it due to retire?
Planned retirement dates are filed for 2 of 2 operating units: Unit GEN1 (2029) and Unit GEN2 (2072).
What does it burn, and where does the fuel come from?
In 2023 it burned other fuels and oil & petroleum.
How much does it spend on fuel?
An estimated $7,402 in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.
How much CO₂ does it emit?
241,749 t in 2023, reported to the EPA — the 1,396th highest of 6,030 US facilities that reported. Up from 201,039 t in 2011.

Related pages

Florida energyAll facilities in the state→Alafia Solar60.0 MW operating capacity→ Durrance60.0 MW operating capacity→ Peace Creek Solar55.4 MW operating capacity→ Riverside Solar55.2 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming