Proposed

A planned 57.5 MW batteries project, filed to come online in 2026.

Planned capacity57.5MW1 unit · not yet in service
CO₂ emittedNot reported2023 · last reported 2019
Reported suppliersNot reported2023 · last deliveries 2019

Location

Floyd County · SOCO · SERC

CO₂ emitted, Mt · 2011–19

0246201120152019
Reported (through 2019)

Generating units

5 of 5 shown · none in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 557.5StorageBatteries2026Proposed
Unit 4578.0Bituminous coalConventional Steam Coal1970Retired 2019
Unit 1125.0Bituminous coalConventional Steam Coal1954Retired 2019
Unit 2125.0Bituminous coalConventional Steam Coal1954Retired 2019
Unit 3125.0Bituminous coalConventional Steam Coal1955Retired 2019

All 5 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; SO₂ scrubber type, sorbent and removal efficiency; NOₓ, particulate and mercury controls with compliance years; cooling system and water source with withdrawal rate; stack height.

See the engineering record →
UnitEventWhenMW
Unit 5new unit202657.5 MW

Who supplies the fuel

2023
No fuel deliveries are reported for 2023. 241 deliveries are on record for 2011–2019.

Delivery history. Subscribe to see every recorded delivery, supplier, mine of origin and transport mode.

See the delivery history →

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Georgia Power Co
Entity type
Investor-Owned Utility
Regulatory status
Regulated
Industry sector
Power Plants
EPA facility ID
1001506
Balancing authority
SOCO
NERC region
SERC
EIA plant ID
708

Common questions

How big is Hammond?
57.5 MW across 1 unit, none of which is in service — the rest planned.
Who owns and operates it?
Operated by Georgia Power Co, filed as investor-owned utility.
Which grid does it sell into?
SOCO (Southern Company Services, Inc. - Trans) is its balancing authority, inside NERC's SERC region.
What does it burn, and where does the fuel come from?
Its generating units are fuelled by bituminous coal.

Related pages

Georgia energyAll facilities in the state→GPC5Power facility→ GPC6Power facility→ Happy Hollow Solar CenterPower facility→ Harllee BranchPower facility→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming