AMERICAN ENERGY ATLAS
Industrial + power·Michigan

GRANGER Grand River Avenue Landfill

Grand Ledge, Clinton County, Michigan · MISO · operated by Energy Developments, Inc d/b/a EDL · owned by Granger Associates Inc

2023 · headline year
Capacity in service3.2MW4 units · biomass
Net generation6.43GWh2023 · reported
CO₂ emitted128,214t2023 · reported to EPA · 2,036th highest of 6,030 in the US
Rank in Michigan#194 (tied)of 258 · by capacity · #8,612 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor23%2023

Location

Clinton County · MISO · RFC

What its on-site power plant burns

2023 · reported

Share of reported fuel consumption

100% Landfill gas · 74,531 MMBtu · reported

CO₂ emitted, t · 2011–2023

050,000100,000150,000201120172023
Reported (through 2023)

Generating units

5 of 5 shown · 3.2 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 2-10.8Landfill gasLandfill Gas1991Operating
Unit 2-30.8Landfill gasLandfill Gas1991Operating
Unit 2-40.8Landfill gasLandfill Gas1996Operating
Unit 2-50.8Landfill gasLandfill Gas1997Operating
Unit 2-20.8Landfill gasLandfill Gas1991Retired 2006

All 5 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Parent company
Granger Associates Inc · 100%
Operating utility
Energy Developments, Inc d/b/a EDL
Entity type
Independent Power Producer
Regulatory status
Not Regulated
Industry sector
Waste
EPA facility ID
1002720
Balancing authority
MISO
NERC region
ReliabilityFirst (RFC)
EIA plant ID
10532

Common questions

How big is GRANGER Grand River Avenue Landfill?
3.2 MW across 4 generating units in service. A further 1 unit is listed as standby, out of service, planned, retired or canceled.
Who owns and operates it?
Owned by Granger Associates Inc (100%) and operated by Energy Developments, Inc d/b/a EDL, filed as independent power producer.
Which grid does it sell into?
MISO (Midcontinent Independent Transmission System Operator, Inc.) is its balancing authority, inside NERC's ReliabilityFirst region.
How old is it?
The capacity-weighted average megawatt here came online in 1994. The oldest operating units are Unit 2-1 and Unit 2-3 (1991); the newest is Unit 2-5 (1997).
When is it due to retire?
No retirement date has been filed for any operating unit at GRANGER Grand River Avenue Landfill. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 its on-site power plant burned landfill gas.
How much CO₂ does it emit?
128,214 t in 2023, reported to the EPA — the 2,036th highest of 6,030 US facilities that reported. Up from 32,489 t in 2011.

Related pages

Michigan energyAll facilities in the state→POET Biorefining - Caro, LLC3.8 MW operating capacity→ Hoist3.4 MW operating capacity→ Waste Management of Michigan Inc3.2 MW operating capacity→ Blue Water Renewables Inc3.2 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming