AMERICAN ENERGY ATLAS
Power·New York

Fuel Cell 3245 Yates Avenue

Bronx County, New York · NYISO · operated by Bronx Community Clean Energy Project LLC

2023 · headline year
Fuel spend$880,9922023 · estimate
Capacity in service5.0MW1 unit · gas
Net generation43.3GWh2023 · reported
Rank in New York#276 (tied)of 1,018 · by capacity · #6,619 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor99%2023

Location

Bronx County · NYISO · NPCC

What it burns

2023 · reported

Share of reported fuel consumption

100% Natural gas · 286,622 MMBtu · reported · $880,992 est.

Reported fuel consumption, MMBtu · 2022–23

0100,000200,000300,00020222023
Reported (through 2023)

Generating units

1 of 1 shown · 5.0 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit C32455.0Natural GasOther Natural Gas2022Operating

1 unit shown. Behind it, AEA holds the full engineering record: ownership stakes where a unit is jointly held.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Bronx Community Clean Energy Project LLC
Entity type
Independent Power Producer
Regulatory status
Not Regulated
Balancing authority
NYISO
NERC region
NPCC
EIA plant ID
64747

Common questions

How big is Fuel Cell 3245 Yates Avenue?
5.0 MW across 1 generating unit in service.
Who owns and operates it?
Operated by Bronx Community Clean Energy Project LLC, filed as independent power producer.
Which grid does it sell into?
NYISO (New York Independent System Operator) is its balancing authority, inside NERC's NPCC region.
How old is it?
The capacity-weighted average megawatt here came online in 2022.
When is it due to retire?
No retirement date has been filed for any operating unit at Fuel Cell 3245 Yates Avenue. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas.
How much does it spend on fuel?
An estimated $880,992 in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.

Related pages

New York energyAll facilities in the state→Flat Rock5.0 MW operating capacity→ Fort Miller Hydroelectric Facility5.0 MW operating capacity→ Gaskill Rd Community Solar Farm CSG5.0 MW operating capacity→ Geneseo Solar5.0 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming