Fuel spend$795,5572023 · estimate
Capacity in service78.6MW2 units · gas + oil
Net generation24.6GWh2023 · reported
CO₂ emitted13,413t2023 · reported to EPA · 5,652nd highest of 6,030 in the US
Rank in New York#80 (tied)of 1,018 · by capacity · #2,800 (tied) of 13,147 US
Reported suppliersNot reported2023 · last deliveries 2011
Capacity factor4%2023
How big is Freeport Power Plant No. 2?
78.6 MW across 2 generating units in service — 60.5 MW of natural gas and 18.1 MW of oil. A further 2 units are listed as standby, out of service, planned, retired or canceled.
Who owns and operates it?
Owned by
Freeport Electric (100%) and operated by Village of Freeport - (NY), filed as municipally owned utility.
Which grid does it sell into?
NYISO (New York Independent System Operator) is its balancing authority, inside NERC's NPCC region.
How old is it?
The capacity-weighted average megawatt here came online in 1997. The oldest operating unit is Unit 3 (1973); the newest is Unit CT5 (2004).
When is it due to retire?
No retirement date has been filed for any operating unit at Freeport Power Plant No. 2. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas and oil & petroleum.
How much does it spend on fuel?
An estimated $795,557 in 2023 — natural gas $755,935 and oil & petroleum $39,622. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.
How much CO₂ does it emit?
13,413 t in 2023, reported to the EPA — the 5,652nd highest of 6,030 US facilities that reported. Down from 29,443 t in 2011.