Morgan County, Colorado
Capacity shown is planned or not in service
A planned 399 MW batteries project, filed to come online in 2028.
| Unit | Capacity MW | Fuel | Technology | Online | Status |
|---|---|---|---|---|---|
| Unit 1 | 199.0 | Solar | Solar Photovoltaic | 2028 | Planned |
| Unit 2 | 150.0 | Storage | Batteries | 2028 | Planned |
| Unit 3 | 49.9 | Storage | Batteries | 2028 | Planned |
All 3 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.
See the engineering record →| Unit | Event | When | MW |
|---|---|---|---|
| Unit 1 | new unit | 2028 | 199 MW |
| Unit 2 | new unit | 2028 | 150 MW |
| Unit 3 | new unit | 2028 | 49.9 MW |