AMERICAN ENERGY ATLAS
Power·Texas

Forest Grove - Dodd

Henderson County, Texas · ERCOT · operated by Vistra Zero LLC

Capacity shown is planned or not in service

Proposed

A planned 200 MW solar photovoltaic project, filed to come online in 2027.

Planned capacity200MW1 unit · not yet in service

Location

Henderson County · ERCOT · TRE

Generating units

2 of 2 shown · none in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit FGPV1200.0SolarSolar Photovoltaic2027Proposed
Unit ESS1100.2StorageBatteriesnot reportedCanceled

All 2 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →
UnitEventWhenMW
Unit FGPV1new unit2027200 MW

Ownership & operations

Operating utility
Vistra Zero LLC
Entity type
Independent Power Producer
Regulatory status
Not Regulated
Balancing authority
ERCOT
NERC region
Texas RE (TRE)
EIA plant ID
64131

Common questions

How big is Forest Grove - Dodd?
200 MW across 1 unit, none of which is in service — the rest planned.
Who owns and operates it?
Operated by Vistra Zero LLC, filed as independent power producer.
Which grid does it sell into?
ERCOT (Electric Reliability Council of Texas, Inc.) is its balancing authority, inside NERC's Texas RE region.
What does it run on?
Solar Photovoltaic (200 MW).

Related pages

Texas energyAll facilities in the state→Florida Gas Transmission Company - VidorIndustrial facility→ FloydadaPower facility→ Fort Bend UtilitiesPower facility→ Fort DavisPower facility→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming