AMERICAN ENERGY ATLAS
Power·Ohio

Fayette Solar

Ross County, Ohio · PJM · operated by National Grid Renewables

Capacity shown is planned or not in service

Proposed

A planned 45.0 MW solar photovoltaic project, filed to come online in 2025.

Planned capacity45.0MW1 unit · not yet in service

Location

Ross County · PJM · RFC

Generating units

1 of 1 shown · none in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit FYTSL45.0SolarSolar Photovoltaic2025Proposed

1 unit shown. Behind it, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →
UnitEventWhenMW
Unit FYTSLnew unit202545.0 MW

Ownership & operations

Operating utility
National Grid Renewables
Entity type
Independent Power Producer
Regulatory status
Not Regulated
Balancing authority
PJM
NERC region
ReliabilityFirst (RFC)
EIA plant ID
67166

Common questions

How big is Fayette Solar?
45.0 MW across 1 unit, none of which is in service — all planned.
Who owns and operates it?
Operated by National Grid Renewables, filed as independent power producer.
Which grid does it sell into?
PJM (PJM Interconnection, LLC) is its balancing authority, inside NERC's ReliabilityFirst region.
What does it run on?
Solar Photovoltaic (45.0 MW).

Related pages

Ohio energyAll facilities in the state→Erie County Sanitary LandfillIndustrial facility→ Eureka Midstream, LLCIndustrial facility→ FDS Co-Generation FacilityPower facility→ Firelands WindPower facility→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming