AMERICAN ENERGY ATLAS
Power·Oregon

Faraday

Clackamas County, Oregon · PGE · operated by Portland General Electric Co

2023 · headline year
Fuel spend$02023 · no purchased fuel
Capacity in service18.0MW2 units · hydro · 1 more on standby or out of service
Rank in Oregon#75 (tied)of 278 · by capacity · #4,745 (tied) of 13,147 US

Location

Clackamas County · PGE · WECC

Generating units

8 of 8 shown · 18.0 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 619.2WaterConventional Hydroelectric1958Out of service
Unit 79.0WaterConventional Hydroelectric2023Operating
Unit 89.0WaterConventional Hydroelectric2023Operating
Unit 44.5WaterConventional Hydroelectric1909Retired 2019
Unit 54.0WaterConventional Hydroelectric1910Retired 2019
Unit 13.1WaterConventional Hydroelectric1907Retired 2019
Unit 23.1WaterConventional Hydroelectric1907Retired 2019
Unit 32.7WaterConventional Hydroelectric1908Retired 2019

All 8 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Ownership & operations

Operating utility
Portland General Electric Co
Entity type
Investor-Owned Utility
Regulatory status
Regulated
Balancing authority
PGE
NERC region
WECC
EIA plant ID
3045

Common questions

How big is Faraday?
18.0 MW across 2 generating units in service. A further 6 units are listed as standby, out of service, planned, retired or canceled.
Who owns and operates it?
Operated by Portland General Electric Co, filed as investor-owned utility.
Which grid does it sell into?
PGE (Portland General Electric Company) is its balancing authority, inside NERC's WECC region.
How old is it?
The capacity-weighted average megawatt here came online in 2023. Every operating unit came online in 2023.
When is it due to retire?
No retirement date has been filed for any operating unit at Faraday. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it run on?
Conventional Hydroelectric (37.2 MW).
How much does it spend on fuel?
Nothing in 2023 — its units in service (conventional hydroelectric) burn no fuel, and it reports no fuel consumption to the EIA.

Related pages

Oregon energyAll facilities in the state→River Mill18.8 MW operating capacity→ Big Cliff18.0 MW operating capacity→ Slide Creek18.0 MW operating capacity→ Green Springs17.2 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming