Lamar County, Texas · ERCOT · operated by BT Ferguson Solar, LLC
Capacity shown is planned or not in service
A planned 302 MW solar photovoltaic project, filed to come online in 2027.
| Unit | Capacity MW | Fuel | Technology | Online | Status |
|---|---|---|---|---|---|
| Unit ECHPV | 201.2 | Solar | Solar Photovoltaic | 2027 | Proposed |
| Unit ECHBA | 100.6 | Storage | Batteries | 2028 | Proposed |
All 2 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.
See the engineering record →| Unit | Event | When | MW |
|---|---|---|---|
| Unit ECHPV | new unit | 2027 | 201 MW |
| Unit ECHBA | new unit | 2028 | 101 MW |