Eastside WWTP

Guilford County, North Carolina · DUK · operated by City Of High Point

2023 · headline year
Fuel spend$48,5612023 · estimate
Capacity in service5.4MW3 units · oil
Net generation213MWh2023 · reported
Rank in North Carolina#182 (tied)of 908 · by capacity · #6,501 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor0%2023

Location

Guilford County · DUK · SERC

What it burns

2023 · reported

Share of reported fuel consumption

100% Oil & petroleum · 1,982 MMBtu · reported · $48,561 est.

Reported fuel consumption, MMBtu · 2011–2023

02,0004,0006,000201120172023
Reported (through 2023)

Generating units

3 of 3 shown · 5.4 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 11.8Distillate oilPetroleum Liquids2004Operating
Unit 21.8Distillate oilPetroleum Liquids2004Operating
Unit 31.8Distillate oilPetroleum Liquids2004Operating

All 3 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
City Of High Point
Entity type
Municipally Owned Utility
Regulatory status
Regulated
Balancing authority
DUK
NERC region
SERC
EIA plant ID
57606

Common questions

How big is Eastside WWTP?
5.4 MW across 3 generating units in service.
Who owns and operates it?
Operated by City Of High Point, filed as municipally owned utility.
Which grid does it sell into?
DUK (Duke Energy Carolinas) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 2004. Every operating unit came online in 2004.
When is it due to retire?
No retirement date has been filed for any operating unit at Eastside WWTP. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned oil & petroleum.
How much does it spend on fuel?
An estimated $48,561 in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.

Related pages

North Carolina energyAll facilities in the state→Woodleaf Solar Facility6.0 MW operating capacity→ Baltimore Church Solar, LLC5.4 MW operating capacity→ Gastonia, Tulip Drive5.4 MW operating capacity→ New Bern5.4 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming