Dominguez Energy Storage

Salt Lake County, Utah · PACE · operated by Dominguez Grid, LLC

Capacity shown is planned or not in service

Proposed

A planned 200 MW batteries project, filed to come online in 2025.

Planned capacity200MW1 unit · not yet in service

Location

Salt Lake County · PACE · WECC

Generating units

1 of 1 shown · none in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit DES1200.0StorageBatteries2025Proposed

1 unit shown. Behind it, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →
UnitEventWhenMW
Unit DES1new unit2025200 MW

Ownership & operations

Operating utility
Dominguez Grid, LLC
Entity type
Independent Power Producer
Regulatory status
Not Regulated
Balancing authority
PACE
NERC region
WECC
EIA plant ID
68596

Common questions

How big is Dominguez Energy Storage?
200 MW across 1 unit, none of which is in service — all planned.
Who owns and operates it?
Operated by Dominguez Grid, LLC, filed as independent power producer.
Which grid does it sell into?
PACE (PacifiCorp - East) is its balancing authority, inside NERC's WECC region.
What does it run on?
Batteries (200 MW).

Related pages

Utah energyAll facilities in the state→Coyote Wash Compressor StationIndustrial facility→ Desert Power LPPower facility→ Dugout Canyon MineIndustrial facility→ eBay - South JordanPower facility→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming