Lafayette, Lafayette Parish, Louisiana · MISO · operated by Lafayette Utilities System

last reported to the EPA in 2014

Retired 2017

Retired — its last generating unit went out of service in 2017, ending 341 MW of capacity.

Retired capacity341MW3 units · none in service
CO₂ emittedNot reported2023 · last reported 2014
Reported suppliersNot reported2023 · last deliveries 2013

Location

Lafayette Parish · MISO · SERC

CO₂ emitted, t · 2011–14

0200,000400,000600,000201120122014
Reported (through 2014)

Generating units

3 of 3 shown · none in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 3187.0Natural GasNatural Gas Steam Turbine1977Retired 2017
Unit 2100.0Natural GasNatural Gas Steam Turbine1970Retired 2017
Unit 153.9Natural GasNatural Gas Steam Turbine1965Retired 2017

All 3 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; NOₓ, particulate and mercury controls with compliance years; cooling system and water source with withdrawal rate; stack height.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023. 24 deliveries are on record for 2011–2013.

Delivery history. Subscribe to see every recorded delivery, supplier, mine of origin and transport mode.

See the delivery history →

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Lafayette Utilities System
Entity type
Municipally Owned Utility
Regulatory status
Regulated
Industry sector
Power Plants
EPA facility ID
1006298
Balancing authority
MISO
NERC region
SERC
Gas pipeline
Enlink Lig LLC
EIA plant ID
1443

Common questions

How big is Doc Bonin?
341 MW across 3 units, none of which is in service — all retired.
Who owns and operates it?
Operated by Lafayette Utilities System, filed as municipally owned utility.
Which grid does it sell into?
MISO (Midcontinent Independent Transmission System Operator, Inc.) is its balancing authority, inside NERC's SERC region.
When is it due to retire?
It has already retired — the last unit retired in 2017.
What does it burn, and where does the fuel come from?
Its generating units are fuelled by natural gas.

Related pages

Louisiana energyAll facilities in the state→Crosstex Processing Services LLC - Blue Water Gas PlantIndustrial facility→ Delta Solar PlantPower facility→ Dolet Hills Power StationPower facility→ Dolet Hills SolarPower facility→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming