Capacity in service50.0MW1 unit · biomass
Net generation310GWh2023 · reported
CO₂ emitted7,363t2023 · reported to EPA · 5,836th highest of 6,030 in the US
Rank in North Carolina#75 (tied)of 908 · by capacity · #3,450 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor71%2023

Location

Craven County · CPLE · SERC

What it burns

2023 · reported

Share of reported fuel consumption

100% Biomass · 4.75 TBtu · reported

CO₂ emitted, t · 2011–2023

05,00010,00015,000201120172023
Reported (through 2023)

Generating units

1 of 1 shown · 50.0 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 1UNI50.0WoodWood/Wood Waste Biomass1990Operating

1 unit shown. Behind it, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; co-firing fuels and fuel-switching times; NOₓ, particulate and mercury controls with compliance years; stack height; ownership stakes where a unit is jointly held.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
CMS Generation Operating Co II
Jointly held units
Atlantic Power Corporation 50% of 1 unit
CMS Generation MI Power LLC 50% of 1 unit
Entity type
Independent Power Producer
Regulatory status
Not Regulated
Industry sector
Power Plants
EPA facility ID
1007732
Balancing authority
CPLE
NERC region
SERC
EIA plant ID
10525

Common questions

How big is Craven County Wood Energy?
50.0 MW across 1 generating unit in service.
Who owns and operates it?
Owned by CMS Energy Corp and Atlantic Power Corp and operated by CMS Generation Operating Co II, filed as independent power producer. 2 owner stakes are filed on jointly held units.
Which grid does it sell into?
CPLE (Duke Energy Progress East) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 1990.
When is it due to retire?
No retirement date has been filed for any operating unit at Craven County Wood Energy. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned biomass.
How much CO₂ does it emit?
7,363 t in 2023, reported to the EPA — the 5,836th highest of 6,030 US facilities that reported. Down from 10,263 t in 2011.

Related pages

North Carolina energyAll facilities in the state→Brantley Solar50.2 MW operating capacity→ Fox Creek Solar50.2 MW operating capacity→ Allen 1 Battery Energy Storage System50.0 MW operating capacity→ Bladen Solar50.0 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming