AMERICAN ENERGY ATLAS
Industrial + power·Idaho

Clearwater Paper Corp

Lewiston, Nez Perce County, Idaho · AVA · operated by Clearwater Paper Corporation · owned by Clearwater Paper Corp

2023 · headline year
Fuel spend$32.7M2023 · estimate
Capacity in service93.8MW2 units · biomass · 2 more on standby or out of service
Net generation383GWh2023 · reported
CO₂ emitted294,660t2023 · reported to EPA · 1,242nd highest of 6,030 in the US
Rank in Idaho#16of 141 · by capacity · #2,577 of 13,147 US
Reported suppliersNot reported2023

Location

Nez Perce County · AVA · WECC

What its on-site power plant burns

2023 · reported

Share of reported fuel consumption

87% Black liquor · 16 TBtu · reported13% Natural gas · 2.41 TBtu · reported · $32.4M est.

Black liquor supplies 87% of the fuel energy its on-site power plant burned in 2023.

CO₂ emitted, t · 2011–2023

0200,000400,000600,000201120172023
Reported (through 2023)

Generating units

4 of 4 shown · 93.8 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit GEN465.0Black liquorWood/Wood Waste Biomass1991Operating
Unit GEN328.8Black liquorWood/Wood Waste Biomass1981Operating
Unit GEN110.0Black liquorWood/Wood Waste Biomass1950Out of service
Unit GEN210.0Black liquorWood/Wood Waste Biomass1977Out of service

All 4 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; co-firing fuels and fuel-switching times; NOₓ, particulate and mercury controls with compliance years; cooling system and water source with withdrawal rate; stack height.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Parent company
Clearwater Paper Corp · 100%
Operating utility
Clearwater Paper Corporation
Entity type
Industrial
Regulatory status
Not Regulated
Industry sector
Pulp and Paper, Waste
EPA facility ID
1004705
Balancing authority
AVA
NERC region
WECC
Gas pipeline
Northwest Pipeline GP
EIA plant ID
50637

Common questions

How big is Clearwater Paper Corp?
93.8 MW across 2 generating units in service. A further 2 units are listed as standby, out of service, planned, retired or canceled.
Who owns and operates it?
Owned by Clearwater Paper Corp (100%) and operated by Clearwater Paper Corporation, filed as industrial.
Which grid does it sell into?
AVA (Avista Corporation) is its balancing authority, inside NERC's WECC region.
How old is it?
The capacity-weighted average megawatt here came online in 1988. The oldest operating unit is Unit GEN3 (1981); the newest is Unit GEN4 (1991).
When is it due to retire?
No retirement date has been filed for any operating unit at Clearwater Paper Corp. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 its on-site power plant burned black liquor and natural gas.
How much does it spend on fuel?
An estimated $32.7M in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.
How much CO₂ does it emit?
294,660 t in 2023, reported to the EPA — the 1,242nd highest of 6,030 US facilities that reported. Up from 288,457 t in 2011.

Related pages

Idaho energyAll facilities in the state→Lucky Peak Power Plant Project101 MW operating capacity→ Franklin Solar Hybrid100 MW operating capacity→ C J Strike82.8 MW operating capacity→ Grand View Solar Two80.0 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming