AMERICAN ENERGY ATLAS
Power·Georgia

CII Methane Management III LFG Plant

Clarke County, Georgia · SOCO · operated by Frontier Operation Services

2023 · headline year
Capacity in service1.6MW1 unit · biomass
Net generation5.4GWh2023 · reported
Rank in Georgia#221 (tied)of 247 · by capacity · #11,073 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor39%2023

Location

Clarke County · SOCO · SERC

What it burns

2023 · reported

Share of reported fuel consumption

100% Landfill gas · 71,505 MMBtu · reported

Reported fuel consumption, MMBtu · 2014–23

050,000100,000150,000201420182023
Reported (through 2023)

Generating units

1 of 1 shown · 1.6 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit GEN11.6Landfill gasLandfill Gas2014Operating

1 unit shown. Behind it, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Frontier Operation Services
Entity type
Independent Power Producer
Regulatory status
Not Regulated
Balancing authority
SOCO
NERC region
SERC
EIA plant ID
59650

Common questions

How big is CII Methane Management III LFG Plant?
1.6 MW across 1 generating unit in service.
Who owns and operates it?
Operated by Frontier Operation Services, filed as independent power producer.
Which grid does it sell into?
SOCO (Southern Company Services, Inc. - Trans) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 2014.
When is it due to retire?
No retirement date has been filed for any operating unit at CII Methane Management III LFG Plant. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned landfill gas.

Related pages

Georgia energyAll facilities in the state→Arnold Cochran1.7 MW operating capacity→ Terrell Riles Stovall1.7 MW operating capacity→ Seminole (GA)1.6 MW operating capacity→ Georgia Power at Jakin GA PV1.5 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming