Beluga, Kenai Peninsula Borough, Alaska · operated by Chugach Electric Assn Inc · owned by Chugach Electric Assoc Inc
| Unit | Capacity MW | Fuel | Technology | Online | Status |
|---|---|---|---|---|---|
| Unit 6 | 76.5 | Natural Gas | Natural Gas Fired Combustion Turbine | 1976 | Out of service |
| Unit 7 | 76.5 | Natural Gas | Natural Gas Fired Combustion Turbine | 1978 | Standby |
| Unit 5 | 68.3 | Natural Gas | Natural Gas Fired Combustion Turbine | 1975 | Standby |
| Unit 3 | 59.1 | Natural Gas | Natural Gas Fired Combustion Turbine | 1972 | Standby |
| Unit 1 | 16.0 | Natural Gas | Natural Gas Fired Combustion Turbine | 1968 | Standby |
| Unit 2 | 16.0 | Natural Gas | Natural Gas Fired Combustion Turbine | 1968 | Out of service |
| Unit 8 | 62.0 | Natural Gas | Natural Gas Fired Combined Cycle | 1982 | Retired 2015 |
All 7 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; NOₓ, particulate and mercury controls with compliance years.
See the engineering record →| Supplier | Fuel | Delivered MMBtu | Tons | Mine of origin | Transport |
|---|---|---|---|---|---|
| Hilcorp Energy Co | Natural gas | 70,323 | n/a | n/a | Pipeline |
Figures are volumes delivered in 2023, not volumes burned. Tons are shown for coal only.
Showing 1 of 2 suppliers. Subscribe to see all 2, every one of the 309 deliveries recorded 2011–2023, mine-level origins, transport mode and the delivered price paid — plus sorting, filtering and Excel export.
See all 2 suppliers →