Kings County, California · CAISO · operated by Westlands Cherry, LLC
Capacity shown is planned or not in service
A planned 400 MW batteries project, filed to come online in 2025.
| Unit | Capacity MW | Fuel | Technology | Online | Status |
|---|---|---|---|---|---|
| Unit CHERY | 249.7 | Solar | Solar Photovoltaic | 2026 | Proposed |
| Unit BESS2 | 110.0 | Storage | Batteries | 2026 | Proposed |
| Unit BESS1 | 40.0 | Storage | Batteries | 2025 | Proposed |
All 3 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.
See the engineering record →| Unit | Event | When | MW |
|---|---|---|---|
| Unit BESS1 | new unit | 2025 | 40.0 MW |
| Unit BESS2 | new unit | 2026 | 110 MW |
| Unit CHERY | new unit | 2026 | 250 MW |