La Paz County, Arizona · AZPS · operated by Copia Power
Capacity shown is planned or not in service
A planned 767 MW solar photovoltaic project, filed to come online in 2026.
| Unit | Capacity MW | Fuel | Technology | Online | Status |
|---|---|---|---|---|---|
| Unit CFPV1 | 166.7 | Solar | Solar Photovoltaic | 2026 | Proposed |
| Unit CFPV2 | 166.7 | Solar | Solar Photovoltaic | 2026 | Proposed |
| Unit CFPV3 | 166.7 | Solar | Solar Photovoltaic | 2026 | Proposed |
| Unit CFB1 | 89.0 | Storage | Batteries | 2026 | Proposed |
| Unit CFB2 | 89.0 | Storage | Batteries | 2026 | Proposed |
| Unit CFB3 | 89.0 | Storage | Batteries | 2026 | Proposed |
All 6 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.
See the engineering record →| Unit | Event | When | MW |
|---|---|---|---|
| Unit CFB1 | new unit | 2026 | 89.0 MW |
| Unit CFB2 | new unit | 2026 | 89.0 MW |
| Unit CFB3 | new unit | 2026 | 89.0 MW |
| Unit CFPV1 | new unit | 2026 | 167 MW |
| Unit CFPV2 | new unit | 2026 | 167 MW |
| Unit CFPV3 | new unit | 2026 | 167 MW |