AMERICAN ENERGY ATLAS
Power·Iowa

Cargill Corn Milling Division

Monroe County, Iowa · MISO · operated by Cargill Inc North America Sweetners

2023 · headline year
Capacity in service20.0MW1 unit · gas · 1 more on standby or out of service
Net generation76.3GWh2023 · reported
Rank in Iowa#127 (tied)of 256 · by capacity · #4,406 (tied) of 13,147 US
Reported suppliersNot reported2023

Location

Monroe County · MISO · MRO

What it burns

2023 · reported

Share of reported fuel consumption

100% Natural gas · 4.77 TBtu · reported

Reported fuel consumption, TBtu · 2011–2023

02.557.5201120172023
Reported (through 2023)

Generating units

2 of 2 shown · 20.0 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit GEN120.0Natural GasNatural Gas Steam Turbine1952Standby
Unit GEN220.0Natural GasNatural Gas Steam Turbine1952Operating

All 2 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; NOₓ, particulate and mercury controls with compliance years.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Cargill Inc North America Sweetners
Entity type
Industrial
Regulatory status
Not Regulated
Balancing authority
MISO
NERC region
MRO
Gas pipeline
Midamerican Energy Company
EIA plant ID
10855

Common questions

How big is Cargill Corn Milling Division?
20.0 MW across 1 generating unit in service. A further 1 unit is listed as standby, out of service, planned, retired or canceled.
Who owns and operates it?
Operated by Cargill Inc North America Sweetners, filed as industrial.
Which grid does it sell into?
MISO (Midcontinent Independent Transmission System Operator, Inc.) is its balancing authority, inside NERC's MRO region.
How old is it?
The capacity-weighted average megawatt here came online in 1952.
When is it due to retire?
No retirement date has been filed for any operating unit at Cargill Corn Milling Division. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas.

Related pages

Iowa energyAll facilities in the state→Crosswind Energy Project21.0 MW operating capacity→ Carroll Area Wind Farm20.7 MW operating capacity→ Shenandoah20.0 MW operating capacity→ Winnebago Wind Power Project20.0 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming