AMERICAN ENERGY ATLAS
Power·Florida

C D McIntosh Jr Power Plant

Lakeland, Polk County, Florida · FMPP · operated by City of Lakeland - (FL) · owned by City of Lakeland Florida

2023 · headline year
Reported fuel cost$43.7M2023 · reported deliveries
Capacity in service606MW9 units · gas + oil · incl. 60.9 MW online after 2023
Net generation1.75TWh2023 · reported
CO₂ emitted699,121t2023 · reported to EPA · 784th highest of 6,030 in the US
Rank in Florida#35of 310 · by capacity · #572 of 13,147 US
Reported suppliers32023 · 21 deliveries

Location

Polk County · FMPP · SERC

What it burns

2023 · reported

Share of reported fuel consumption

100% Natural gas · 12.8 TBtu · reported

CO₂ emitted, Mt · 2011–2023

0123201120172023
Reported (through 2023)

Generating units

17 of 17 shown · 606 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 5CT249.0Natural GasNatural Gas Fired Combined Cycle2001Operating
Unit 5ST135.0Natural GasNatural Gas Fired Combined Cycle2002Operating
Unit GT2130.0Natural GasNatural Gas Fired Combustion Turbine2020Operating
Unit GT126.6Natural GasNatural Gas Fired Combustion Turbine1973Operating
Unit IC620.3Natural GasNatural Gas Internal Combustion Engine2024Operating
Unit IC720.3Natural GasNatural Gas Internal Combustion Engine2024Operating
Unit IC820.3Natural GasNatural Gas Internal Combustion Engine2024Operating
Unit IC12.5Distillate oilPetroleum Liquids1970Operating
Unit IC22.5Distillate oilPetroleum Liquids1970Operating
Unit IC320.3Natural GasNatural Gas Internal Combustion Engine2025Proposed
Unit IC420.3Natural GasNatural Gas Internal Combustion Engine2025Proposed
Unit IC520.3Natural GasNatural Gas Internal Combustion Engine2025Proposed
Unit 3363.8Bituminous coalConventional Steam Coal1982Retired 2021
Unit ST2126.0Natural GasNatural Gas Steam Turbine1976Retired 2020
Unit ST1103.5Natural GasNatural Gas Steam Turbine1971Retired 2015
Unit 4288.0Petroleum cokePetroleum Cokenot reportedCanceled
Unit PV616.0SolarSolar Photovoltaicnot reportedCanceled

All 17 units shown. Behind each one, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; co-firing fuels and fuel-switching times; SO₂ scrubber type, sorbent and removal efficiency; NOₓ, particulate and mercury controls with compliance years; cooling system and water source with withdrawal rate; stack height; ownership stakes where a unit is jointly held.

See the engineering record →
UnitEventWhenMW
Unit IC3new unit202520.3 MW
Unit IC4new unit202520.3 MW
Unit IC5new unit202520.3 MW

Who supplies the fuel

1 of 3 suppliers · delivered in 2023
SupplierFuelDelivered TBtuTonsMine of originTransport
Gulf StreamNatural gas5.92n/an/aPipeline

Figures are volumes delivered in 2023, not volumes burned. Tons are shown for coal only.

Showing 1 of 3 suppliers. Subscribe to see all 3, every one of the 492 deliveries recorded 2011–2023, mine-level origins, transport mode and the delivered price paid — plus sorting, filtering and Excel export.

See all 3 suppliers →

In the Atlas

Open in the Atlas →

Ownership & operations

Parent company
City of Lakeland Florida · 100%
Operating utility
City of Lakeland - (FL)
Jointly held units
City of Lakeland - (FL) 60% of 1 unit
Orlando Utilities Comm 40% of 1 unit
Entity type
Municipally Owned Utility
Regulatory status
Regulated
Industry sector
Power Plants
EPA facility ID
1001500
Balancing authority
FMPP
NERC region
SERC
Gas pipeline
Florida Gas Transmission Company, Gulfstream Natural Gas System LLC
EIA plant ID
676

Common questions

How big is C D McIntosh Jr Power Plant?
606 MW across 9 generating units in service — 601 MW of natural gas and 5.0 MW of oil. A further 8 units are listed as standby, out of service, planned, retired or canceled.
Who owns and operates it?
Owned by City of Lakeland Florida (100%) and operated by City of Lakeland - (FL), filed as municipally owned utility. 2 owner stakes are filed on jointly held units.
Which grid does it sell into?
FMPP (Florida Municipal Power Pool) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 2006. The oldest operating units are Unit IC1 and Unit IC2 (1970); the newest are Unit IC6, Unit IC7 and Unit IC8 (2024).
When is it due to retire?
No retirement date has been filed for any operating unit at C D McIntosh Jr Power Plant. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas. Natural gas came from 3 suppliers in 2023.
How much does it spend on fuel?
Its fuel receipts report a delivered cost of $43.7M in 2023.
How much CO₂ does it emit?
699,121 t in 2023, reported to the EPA — the 784th highest of 6,030 US facilities that reported. Down from 2.34 Mt in 2011.

Related pages

Florida energyAll facilities in the state→Lansing Smith Generating Plant662 MW operating capacity→ Osprey Energy Center644 MW operating capacity→ Osceola580 MW operating capacity→ Shady Hills541 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming