Fuel spend$62,8182023 · estimate
Capacity in service10.8MW6 units · oil
Net generation237MWh2023 · reported
Rank in Ohio#91 (tied)of 189 · by capacity · #5,285 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor0%2023

Location

Williams County · PJM · RFC

What it burns

2023 · reported

Share of reported fuel consumption

100% Oil & petroleum · 2,979 MMBtu · reported · $62,818 est.

Reported fuel consumption, MMBtu · 2011–2023

03,0006,0009,000201120172023
Reported (through 2023)

Generating units

6 of 6 shown · 10.8 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 11.8Distillate oilPetroleum Liquids1999Operating
Unit 21.8Distillate oilPetroleum Liquids1999Operating
Unit 31.8Distillate oilPetroleum Liquids1999Operating
Unit 41.8Distillate oilPetroleum Liquids1999Operating
Unit 51.8Distillate oilPetroleum Liquids1999Operating
Unit 61.8Distillate oilPetroleum Liquids1999Operating

All 6 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
American Mun Power-Ohio, Inc
Entity type
Municipally Owned Utility
Regulatory status
Regulated
Balancing authority
PJM
NERC region
ReliabilityFirst (RFC)
EIA plant ID
7779

Common questions

How big is Bryan Peaking?
10.8 MW across 6 generating units in service.
Who owns and operates it?
Operated by American Mun Power-Ohio, Inc, filed as municipally owned utility.
Which grid does it sell into?
PJM (PJM Interconnection, LLC) is its balancing authority, inside NERC's ReliabilityFirst region.
How old is it?
The capacity-weighted average megawatt here came online in 1999. Every operating unit came online in 1999.
When is it due to retire?
No retirement date has been filed for any operating unit at Bryan Peaking. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned oil & petroleum.
How much does it spend on fuel?
An estimated $62,818 in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.

Related pages

Ohio energyAll facilities in the state→DG AMP Solar Piqua Manier12.6 MW operating capacity→ Bowling Green Energy Storage Project12.0 MW operating capacity→ Cleveland Peaking10.8 MW operating capacity→ Dover Peaking10.8 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming