Broshco Fabricated Products

Richland County, Ohio · PJM · operated by Broshco Fabricated Products

2023 · headline year
Fuel spend$195,8572023 · estimate
Capacity in service4.7MW4 units · gas
Net generation2.85GWh2023 · reported
Rank in Ohio#117of 189 · by capacity · #7,743 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor7%2023

Location

Richland County · PJM · RFC

What it burns

2023 · reported

Share of reported fuel consumption

100% Natural gas · 27,127 MMBtu · reported · $195,857 est.

Reported fuel consumption, MMBtu · 2013–2023

0200,000400,000600,000201320182023
Reported (through 2023)

Generating units

4 of 4 shown · 4.7 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 11.2Natural GasNatural Gas Fired Combustion Turbine2001Operating
Unit 21.2Natural GasNatural Gas Fired Combustion Turbine2001Operating
Unit 31.2Natural GasNatural Gas Fired Combustion Turbine2001Operating
Unit 41.1Natural GasNatural Gas Fired Combustion Turbine2005Operating

All 4 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
Broshco Fabricated Products
Entity type
Industrial
Regulatory status
Not Regulated
Balancing authority
PJM
NERC region
ReliabilityFirst (RFC)
EIA plant ID
59373

Common questions

How big is Broshco Fabricated Products?
4.7 MW across 4 generating units in service.
Who owns and operates it?
Operated by Broshco Fabricated Products, filed as industrial.
Which grid does it sell into?
PJM (PJM Interconnection, LLC) is its balancing authority, inside NERC's ReliabilityFirst region.
How old is it?
The capacity-weighted average megawatt here came online in 2002. The oldest operating units are Unit 1, Unit 2 and Unit 3 (2001); the newest is Unit 4 (2005).
When is it due to retire?
No retirement date has been filed for any operating unit at Broshco Fabricated Products. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas.
How much does it spend on fuel?
An estimated $195,857 in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.

Related pages

Ohio energyAll facilities in the state→Versailles Peaking5.4 MW operating capacity→ Brown County LFGTE Power Station4.8 MW operating capacity→ Cooper Farms VW Project4.5 MW operating capacity→ Haviland Plastic Products4.5 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming