AMERICAN ENERGY ATLAS
Power·Pennsylvania

Blue Ridge Landfill Gas to Energy

Scotland, Franklin County, Pennsylvania · PJM · operated by NextEra Renewable Fuels, LLC

last reported to the EPA in 2015

2023 · headline year
Capacity in service6.4MW4 units · biomass
Net generation45.9GWh2023 · reported
CO₂ emittedNot reported2023 · last reported 2015
Rank in Pennsylvania#177 (tied)of 256 · by capacity · #6,264 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor82%2023

Location

Franklin County · PJM · RFC

What it burns

2023 · reported

Share of reported fuel consumption

100% Landfill gas · 544,304 MMBtu · reported

CO₂ emitted, t · 2013–15

0100200300201320142015
Reported (through 2015)

Generating units

4 of 4 shown · 6.4 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit GEN11.6Landfill gasLandfill Gas2013Operating
Unit GEN21.6Landfill gasLandfill Gas2013Operating
Unit GEN31.6Landfill gasLandfill Gas2013Operating
Unit GEN41.6Landfill gasLandfill Gas2013Operating

All 4 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
NextEra Renewable Fuels, LLC
Entity type
Independent Power Producer
Regulatory status
Not Regulated
Industry sector
Power Plants
EPA facility ID
1011030
Balancing authority
PJM
NERC region
ReliabilityFirst (RFC)
EIA plant ID
57466

Common questions

How big is Blue Ridge Landfill Gas to Energy?
6.4 MW across 4 generating units in service.
Who owns and operates it?
Operated by NextEra Renewable Fuels, LLC, filed as independent power producer.
Which grid does it sell into?
PJM (PJM Interconnection, LLC) is its balancing authority, inside NERC's ReliabilityFirst region.
How old is it?
The capacity-weighted average megawatt here came online in 2013. Every operating unit came online in 2013.
When is it due to retire?
No retirement date has been filed for any operating unit at Blue Ridge Landfill Gas to Energy. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned landfill gas.

Related pages

Pennsylvania energyAll facilities in the state→Falling Spring7.2 MW operating capacity→ East Campus Steam Plant7.0 MW operating capacity→ Epp Renewable Energy Llc/cumberland Cty6.4 MW operating capacity→ Pny Bess LLC6.2 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming