AMERICAN ENERGY ATLAS
Power·Minnesota

Blue Lake Generating Plant

Shakopee, Scott County, Minnesota · MISO · operated by Northern States Power Co - Minnesota · owned by Xcel Energy Inc

2023 · headline year
Fuel spend$11M2023 · estimate
Capacity in service559MW6 units · gas + oil
Net generation63.1GWh2023 · reported
CO₂ emitted48,735t2023 · reported to EPA · 3,744th highest of 6,030 in the US
Rank in Minnesota#10of 767 · by capacity · #632 of 13,147 US
Reported suppliersNot reported2023 · last deliveries 2023
Capacity factor1%2023

Location

Scott County · MISO · MRO

What it burns

2023 · reported

Share of reported fuel consumption

100% Natural gas · 775,778 MMBtu · reported · $11M est.

CO₂ emitted, t · 2011–2023

0100,000200,000300,000201120172023
Reported (through 2023)

Generating units

9 of 9 shown · 559 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 7166.3Natural GasNatural Gas Fired Combustion Turbine2005Operating
Unit 8166.3Natural GasNatural Gas Fired Combustion Turbine2005Operating
Unit 156.7Distillate oilPetroleum Liquids1974Operating
Unit 256.7Distillate oilPetroleum Liquids1974Operating
Unit 356.7Distillate oilPetroleum Liquids1974Operating
Unit 456.7Distillate oilPetroleum Liquids1974Operating
Unit BLL099.8Natural GasNatural Gas Internal Combustion Engine2025Proposed
Unit BLL109.8Natural GasNatural Gas Internal Combustion Engine2025Proposed
Unit BLL119.8Natural GasNatural Gas Internal Combustion Engine2025Proposed

All 9 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →
UnitEventWhenMW
Unit BLL09new unit20259.8 MW
Unit BLL10new unit20259.8 MW
Unit BLL11new unit20259.8 MW
Unit 1retirement2025-0556.7 MW
Unit 2retirement2025-0556.7 MW
Unit 3retirement2025-0556.7 MW
Unit 4retirement2025-0556.7 MW

Who supplies the fuel

2023
No fuel deliveries are reported for 2023. 880 deliveries are on record for 2011–2023.

Delivery history. Subscribe to see every recorded delivery, supplier, mine of origin and transport mode.

See the delivery history →

In the Atlas

Open in the Atlas →

Ownership & operations

Parent company
Xcel Energy Inc · 100%
Operating utility
Northern States Power Co - Minnesota
Entity type
Investor-Owned Utility
Regulatory status
Regulated
Industry sector
Power Plants
EPA facility ID
1000424
Balancing authority
MISO
NERC region
MRO
EIA plant ID
8027

Common questions

How big is Blue Lake Generating Plant?
559 MW across 6 generating units in service — 333 MW of natural gas and 227 MW of oil. A further 3 units are listed as standby, out of service, planned, retired or canceled.
Who owns and operates it?
Owned by Xcel Energy Inc (100%) and operated by Northern States Power Co - Minnesota, filed as investor-owned utility.
Which grid does it sell into?
MISO (Midcontinent Independent Transmission System Operator, Inc.) is its balancing authority, inside NERC's MRO region.
How old is it?
The capacity-weighted average megawatt here came online in 1992. The oldest operating units are Unit 1, Unit 2, Unit 3 and Unit 4 (1974); the newest are Unit 7 and Unit 8 (2005).
When is it due to retire?
Planned retirement dates are filed for 4 of 6 operating units: Unit 1 (2025), Unit 2 (2025), Unit 3 (2025) and Unit 4 (2025).
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas.
How much does it spend on fuel?
An estimated $11M in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.
How much CO₂ does it emit?
48,735 t in 2023, reported to the EPA — the 3,744th highest of 6,030 US facilities that reported. Down from 61,347 t in 2011.

Also at this site

Blue Lake SolarSame site · operating→

Related pages

Minnesota energyAll facilities in the state→Riverside (1927)586 MW operating capacity→ Black Dog563 MW operating capacity→ Lakefield Junction Generating536 MW operating capacity→ Pleasant Valley Station468 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming