Power·Virginia
Bayview
Northampton County, Virginia · PJM · operated by Calpine Mid-Atlantic Generation LLC
Standby2023 · headline year
Fuel spend$303,9422023 · estimate
Standby capacity12.0MW6 units · none in service
Net generation1.55GWh2023 · reported
Reported suppliersNot reported2023
Location
What it burns
2023 · reported
Share of reported fuel consumption
100% Oil & petroleum · 15,418 MMBtu · reported · $303,942 est.
Reported fuel consumption, MMBtu · 2011–2023
Reported (through 2023)
Generating units
6 of 6 shown · none in service
All 6 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.
See the engineering record →
Who supplies the fuel
2023
No fuel deliveries are reported for 2023.
Ownership & operations
- Operating utility
- Calpine Mid-Atlantic Generation LLC
- Entity type
- Independent Power Producer
- Regulatory status
- Not Regulated
- Balancing authority
- PJM
- NERC region
- ReliabilityFirst (RFC)
- EIA plant ID
- 3782
Common questions
How big is Bayview?
12.0 MW across 6 units, none of which is in service — all on standby or out of service.
Who owns and operates it?
Operated by Calpine Mid-Atlantic Generation LLC, filed as independent power producer.
Which grid does it sell into?
PJM (PJM Interconnection, LLC) is its balancing authority, inside NERC's ReliabilityFirst region.
What does it burn, and where does the fuel come from?
In 2023 it burned oil & petroleum.
How much does it spend on fuel?
An estimated $303,942 in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.
Related pages
Select a state