Operated by Duke Energy Florida, LLC, filed as investor-owned utility.
Which grid does it sell into?
FPC (Progress Energy Florida) is its balancing authority, inside NERC's SERC region.
How old is it?
The capacity-weighted average megawatt here came online in 1973. Every operating unit came online in 1973.
When is it due to retire?
No retirement date has been filed for any operating unit at Bayboro. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned oil & petroleum.
How much does it spend on fuel?
An estimated $1.44M in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.