Power·Florida
Auburndale Peaker Energy Center
Auburndale, Polk County, Florida
last reported to the EPA in 2018
Retired 2018
Retired — its last generating unit went out of service in 2018, ending 130 MW of capacity.
Retired capacity130MW1 unit · none in service
CO₂ emittedNot reported2023 · last reported 2018
Reported suppliersNot reported2023 · last deliveries 2011
CO₂ emitted, t · 2011–18
Reported (through 2018)
Generating units
1 of 1 shown · none in service
1 unit shown. Behind it, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.
See the engineering record →
Who supplies the fuel
2023
No fuel deliveries are reported for 2023. 12 deliveries are on record for 2011.
Delivery history. Subscribe to see every recorded delivery, supplier, mine of origin and transport mode.
See the delivery history →
In the Atlas
- Spend and volume trend8 years
- Suppliers and contracts1 supplier, 12 deliveries
- Monthly receipts12 months
Open in the Atlas →
Ownership & operations
- Industry sector
- Power Plants
- EPA facility ID
- 1000551
Common questions
How big is Auburndale Peaker Energy Center?
130 MW across 1 unit, none of which is in service — all retired.
When is it due to retire?
It has already retired — the last unit retired in 2018.
What does it burn, and where does the fuel come from?
Its generating units are fuelled by natural gas.