AMERICAN ENERGY ATLAS
Power·Nebraska

Arnold

Custer County, Nebraska

Retired 2022

Retired — its last generating unit went out of service in 2022, ending 1.1 MW of capacity.

Retired capacity1.1MW4 units · none in service
Reported suppliersNot reported2023

Location

Custer County

Reported fuel consumption, MMBtu · 2011–14

0300600900201120122014
Reported (through 2014)

Generating units

4 of 4 shown · none in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit 10.5Distillate oilPetroleum Liquids1960Retired 2022
Unit 40.3Distillate oilPetroleum Liquids1946Retired 2022
Unit 30.2Distillate oilPetroleum Liquids1942Retired 2022
Unit 2A0.1Distillate oilPetroleum Liquids1937Retired 2022

All 4 units shown. Behind each one, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

EIA plant ID
2216

Common questions

How big is Arnold?
1.1 MW across 4 units, none of which is in service — all retired.
When is it due to retire?
It has already retired — the last unit retired in 2022.
What does it burn, and where does the fuel come from?
Its generating units are fuelled by distillate oil.

Related pages

Nebraska energyAll facilities in the state→Bertrand Compressor Station12,437 t CO₂ in 2023→ AltEn, LLCIndustrial facility→ Aurora East, LLCIndustrial facility→ BenkelmanPower facility→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming