APG Combined Heat and Power Plant

Harford County, Maryland · PJM · operated by US Dept of Army, Garrison, APG

2023 · headline year
Fuel spend$11.3M2023 · estimate
Capacity in service7.9MW1 unit · gas
Net generation49.7GWh2023 · reported
Rank in Maryland#49of 210 · by capacity · #5,980 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor72%2023

Location

Harford County · PJM · RFC

What it burns

2023 · reported

Share of reported fuel consumption

100% Natural gas · 884,493 MMBtu · reported · $11.3M est.

Reported fuel consumption, MMBtu · 2016–23

0500,0001,000,0001,500,000201620202023
Reported (through 2023)

Generating units

1 of 1 shown · 7.9 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit GEN17.9Natural GasNatural Gas Fired Combustion Turbine2016Operating

1 unit shown. Behind it, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Operating utility
US Dept of Army, Garrison, APG
Entity type
Federally Owned Utility
Regulatory status
Not Regulated
Balancing authority
PJM
NERC region
ReliabilityFirst (RFC)
EIA plant ID
61282

Common questions

How big is APG Combined Heat and Power Plant?
7.9 MW across 1 generating unit in service.
Who owns and operates it?
Operated by US Dept of Army, Garrison, APG, filed as federally owned utility.
Which grid does it sell into?
PJM (PJM Interconnection, LLC) is its balancing authority, inside NERC's ReliabilityFirst region.
How old is it?
The capacity-weighted average megawatt here came online in 2016.
When is it due to retire?
No retirement date has been filed for any operating unit at APG Combined Heat and Power Plant. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 it burned natural gas.
How much does it spend on fuel?
An estimated $11.3M in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.

Related pages

Maryland energyAll facilities in the state→Costen Solar8.8 MW operating capacity→ Union Bridge Solar8.2 MW operating capacity→ Gateway Solar7.6 MW operating capacity→ Blue Star7.5 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming