Fuel spend$6.17M2023 · estimate
Capacity in service6.0MW1 unit · coal
Net generation42.8GWh2023 · reported
CO₂ emitted370,074t2023 · reported to EPA · 1,118th highest of 6,030 in the US
Rank in North Dakota#52of 55 · by capacity · #6,337 (tied) of 13,147 US
Reported suppliersNot reported2023
Capacity factor81%2023

Location

Pembina County · MISO · MRO

What its on-site power plant burns

2023 · reported

Share of reported fuel consumption

100% Coal · 2.26 TBtu · reported · $5.37M est.

CO₂ emitted, t · 2011–2023

0200,000400,000600,000201120172023
Reported (through 2023)

Generating units

1 of 1 shown · 6.0 MW in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit G16.0SubbituminousConventional Steam Coal1965Operating

1 unit shown. Behind it, AEA holds the generator-level record: start-up fuels, planned uprates, derates and retirements.

See the engineering record →

Who supplies the fuel

2023
No fuel deliveries are reported for 2023.

In the Atlas

Open in the Atlas →

Ownership & operations

Parent company
American Crystal Sugar Co · 100%
Operating utility
American Crystal Sugar Co
Entity type
Industrial
Regulatory status
Not Regulated
Industry sector
Minerals, Waste
EPA facility ID
1006878
Balancing authority
MISO
NERC region
MRO
EIA plant ID
54213

Common questions

How big is American Crystal Sugar Company - Drayton?
6.0 MW across 1 generating unit in service.
Who owns and operates it?
Owned by American Crystal Sugar Co (100%) and operated by American Crystal Sugar Co, filed as industrial.
Which grid does it sell into?
MISO (Midcontinent Independent Transmission System Operator, Inc.) is its balancing authority, inside NERC's MRO region.
How old is it?
The capacity-weighted average megawatt here came online in 1965.
When is it due to retire?
No retirement date has been filed for any operating unit at American Crystal Sugar Company - Drayton. An absent date means none is currently filed, not that the plant will run indefinitely.
What does it burn, and where does the fuel come from?
In 2023 its on-site power plant burned coal.
How much does it spend on fuel?
An estimated $6.17M in 2023. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.
How much CO₂ does it emit?
370,074 t in 2023, reported to the EPA — the 1,118th highest of 6,030 US facilities that reported. Up from 312,177 t in 2011.

Related pages

North Dakota energyAll facilities in the state→Velva Windfarm LLC11.9 MW operating capacity→ Tesoro Mandan Cogeneration Plant7.5 MW operating capacity→ Northern Border Pipeline Glen Ullin CS#65.3 MW operating capacity→ Minot Wind Project4.5 MW operating capacity→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming