Power·Maryland

AES Warrior Run

Cumberland, Allegany County, Maryland · PJM · operated by AES WR Ltd Partnership · owned by AES Corp

Generating units retired 20242023 · headline year

Retired — its last generating unit went out of service in 2024, ending 229 MW of capacity, 100% coal by fuel energy in 2023.

Fuel spend$28.6M2023 · estimate
Retired capacity229MW1 unit · none in service
CO₂ emitted781,434t2023 · reported to EPA · 730th highest of 6,030 in the US
Rank in Maryland#7of 46 · by reported CO₂ · #730 of 6,030 US

Location

Allegany County · PJM · RFC

What it burns

2023 · reported

Share of reported fuel consumption

100% Coal · 7.84 TBtu · reported · $28.1M est.

CO₂ emitted, Mt · 2011–2023

00.511.5201120172023
Reported (through 2023)

Generating units

1 of 1 shown · none in service
UnitCapacity MWFuelTechnologyOnlineStatus
Unit GEN1229.0Bituminous coalConventional Steam Coal1999Retired 2024

1 unit shown. Behind it, AEA holds the full engineering record: boiler design and firing type, efficiency at full and half load, turndown ratio; SO₂ scrubber type, sorbent and removal efficiency; NOₓ, particulate and mercury controls with compliance years; cooling system and water source with withdrawal rate; stack height.

See the engineering record →

In the Atlas

Open in the Atlas →

Ownership & operations

Parent company
AES Corp · 100%
Operating utility
AES WR Ltd Partnership
Entity type
Independent Power Producer
Regulatory status
Not Regulated
Industry sector
Power Plants, Suppliers of CO2
EPA facility ID
1001223
Balancing authority
PJM
NERC region
ReliabilityFirst (RFC)
EIA plant ID
10678

Common questions

How big is AES Warrior Run?
229 MW across 1 unit, none of which is in service — all retired.
Who owns and operates it?
Owned by AES Corp (100%) and operated by AES WR Ltd Partnership, filed as independent power producer.
Which grid does it sell into?
PJM (PJM Interconnection, LLC) is its balancing authority, inside NERC's ReliabilityFirst region.
When is it due to retire?
It has already retired — the last unit retired in 2024.
What does it burn, and where does the fuel come from?
In 2023 it burned coal.
How much does it spend on fuel?
An estimated $28.6M in 2023 — coal $28.1M and oil & petroleum $438,994. No agency publishes this site's whole fuel bill, so this is an AEA estimate rather than a reported figure.
How much CO₂ does it emit?
781,434 t in 2023, reported to the EPA — the 730th highest of 6,030 US facilities that reported. Down from 1.49 Mt in 2011.

Also at this site

AES Warrior Run Energy Storage ProjectSame site · retired→

Related pages

Maryland energyAll facilities in the state→Heidelberg Materials US Cement LLC1.86 Mt CO₂ in 2023→ Cove Point LNG Facility1.15 Mt CO₂ in 2023→ Holcim (US), Inc.451,527 t CO₂ in 2023→ Central Sanitary Landfill121,695 t CO₂ in 2023→

Select a state

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaGuamHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaPuerto RicoRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUS Virgin IslandsUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming