Kaufman County, Texas · ERCOT · operated by Ables Springs Solar, LLC
Capacity shown is planned or not in service
A planned 251 MW solar photovoltaic project, filed to come online in 2025.
| Unit | Capacity MW | Fuel | Technology | Online | Status |
|---|---|---|---|---|---|
| Unit SOLAR | 151.0 | Solar | Solar Photovoltaic | 2025 | Proposed |
| Unit BESS | 100.0 | Storage | Batteries | 2025 | Proposed |
All 2 units shown. Behind each one, AEA holds the full engineering record: ownership stakes where a unit is jointly held.
See the engineering record →| Unit | Event | When | MW |
|---|---|---|---|
| Unit BESS | new unit | 2025 | 100 MW |
| Unit SOLAR | new unit | 2025 | 151 MW |